7 - Software Engineering Management - 7 - Software Engineering Measurement


The importance of measurement and its role in better management and engineering practices is widely acknowledged (see Measurement in the Engineering Foundations KA). Effective measurement has become one of the cornerstones of organizational maturity. Measurement can be applied to organizations, projects, processes, and work products. In this section the focus is on the application of measurement at the levels of projects, processes, and work products.
This section follows the IEEE 15939:2008 standard [6], which describes a process to define the activities and tasks necessary to implement a software measurement process. The standard also includes a measurement information model.

Establish and Sustain Measurement Commitment  

• Requirements for measurement. Each measurement endeavor should be guided by organizational objectives and driven by a set of measurement requirements established by the organization and the project (for example, an organizational objective might be “first-to-market with new products”).
• Scope of measurement. The organizational unit to which each measurement requirement is to be applied should be established. This may consist of a functional area, a single project, a single site, or an entire enterprise. The temporal scope of the measurement effort should also be considered because time series of some measurements may be required; for example, to calibrate estimation models (see section 2.3, Effort, Schedule, and Cost Estimation).
• Team commitment to measurement. The commitment should be formally established, communicated, and supported by resources (see next item).
• Resources for measurement. An organization’s commitment to measurement is an essential factor for success, as evidenced by the assignment of resources for implementing the measurement process. Assigning resources includes allocation of responsibility for the various tasks of the measurement process (such as analyst and librarian). Adequate funding, training, tools, and support to conduct the process should also be allocated.

Plan the Measurement Process 
• Characterize the organizational unit. The organizational unit provides the context for measurement, so the organizational context should be made explicit, including the constraints that the organization imposes on the measurement process. The characterization can be stated in terms of organizational processes, application domains, technology, organizational interfaces, and organizational structure.
• Identify information needs. Information needs are based on the goals, constraints, risks, and problems of the organizational unit. They may be derived from business, organizational, regulatory, and/or product objectives. They should be identified and prioritized. Then a subset of objectives to be addressed can be selected, documented, communicated, and reviewed by stakeholders.
• Select measures. Candidate measures should be selected, with clear links to the information needs. Measures should be selected based on the priorities of the information needs and other criteria such as cost of collection, degree of process disruption during collection, ease of obtaining accurate, consistent data, and ease of analysis and reporting. Because internal quality characteristics (see Models and Quality Characteristics in the Software Quality KA) are often not contained in the contractually binding software requirements, it is important to consider measuring the internal quality of the software to provide an early indicator of potential issues that may impact external stakeholders.
• Define data collection, analysis, and reporting procedures. This encompasses collection procedures and schedules, storage, verification, analysis, reporting, and configuration management of data.
• Select criteria for evaluating the information products. Criteria for evaluation are influenced by the technical and business objectives of the organizational unit. Information products include those associated with the product being produced, as well as those associated with the processes being used to manage and measure the project.
• Provide resources for measurement tasks. The measurement plan should be reviewed and approved by the appropriate stakeholders to include all data collection procedures; storage, analysis, and reporting procedures; evaluation criteria; schedules; and responsibilities. Criteria for reviewing these artifacts should have been established at the organizational-unit level or higher and should be used as the basis for these reviews. Such criteria should take into consideration previous experience, availability of resources, and potential disruptions to projects when changes from current practices are proposed. Approval demonstrates commitment to the measurement process.
• Identify resources to be made available for implementing the planned and approved measurement tasks. Resource availability may be staged in cases where changes are to be piloted before widespread deployment. Consideration should be paid to the resources necessary for successful deployment of new procedures or measures.
• Acquire and deploy supporting technologies. This includes evaluation of available supporting technologies, selection of the most appropriate technologies, acquisition of those technologies, and deployment of those technologies.

Perform the Measurement Process
• Integrate measurement procedures with relevant software processes. The measurement procedures, such as data collection, should be integrated into the software processes they are measuring. This may involve changing current software processes to accommodate data collection or generation activities. It may also involve analysis of current software processes to minimize additional effort and evaluation of the effect on employees to ensure that the measurement procedures will be accepted. Morale issues and other human factors should be considered. In addition, the measurement procedures should be communicated to those providing the data. Training and support may also need to be provided. Data analysis and reporting procedures are typically integrated into organizational and/ or project processes in a similar manner.
• Collect data. Data should be collected, verified, and stored. Collection can sometimes be automated by using software engineering management tools (see topic 7, Software Engineering Management Tools) to analyze data and develop reports. Data may be aggregated, transformed, or recoded as part of the analysis process, using a degree of rigor appropriate to the nature of the data and the information needs. The results of this analysis are typically indicators such as graphs, numbers, or other indications that will be interpreted, resulting in conclusions and recommendations to be presented to stakeholders (see Statistical Analysis in the Engineering Foundations KA). The results and conclusions are usually reviewed, using a process defined by the organization (which may be formal or informal). Data providers and measurement users should participate in reviewing the data to ensure that they are meaningful and accurate and that they can result in reasonable actions.
• Communicate results. Information products should be documented and communicated to users and stakeholders.

Evaluate Measurement
• Evaluate information products and the measurement process against specified evaluation criteria and determine strengths and weaknesses of the information products or process, respectively. Evaluation may be performed by an internal process or an external audit; it should include feedback from measurement users. Lessons learned should be recorded in an appropriate database.
• Identify potential improvements. Such improvements may be changes in the format of indicators, changes in units measured, or reclassification of measurement categories. The costs and benefits of potential improvements should be determined and appropriate improvement actions should be reported.
• Communicate proposed improvements to the measurement process owner and stakeholders for review and approval. Also, lack of potential improvements should be communicated if the analysis fails to identify any improvements.

Back - 6 - Closure
Next - 8 - Software Engineering Management Tools
Home - Software Engineering Management
Main - The BOK

Published on : 30-May-2018
Ref no : DTC-WPUB-000058

About Author

My photo
Wan Mohd Adzha CAPM,MCPD,MCSD,MCSE
Passionate about new technology ( Software Engineering ) and how to build,manage and maintain them

Comments